Sound Targeting Platform

Andrew Lenharth
Michael Schaffer
Quang Luu




 

Development Schedule


WEEK 1
  • Team Assignments
  • Decide on project
  • Preliminary design
  • Web page design
WEEK 2
  • Layout detailed design
  • Determine preliminary parts list
  • Obtain spec sheets - motors, codec, microphones, ADC
  • *Due: Project Proposals

WEEK 3

 

  • Understand correlation
  • Determine audio sampling rates
WEEK 4
  • Start designing correlator
  • Interface microphones to FPGA
  • Interface step motors to FPGA
*Due: Preliminary Design Package
WEEK 5
  • Build analog filters for microphones
  • Build circuit to drive step motors

*Due: Revised Preliminary Design Package

WEEK 6
  • Flex time for finishing weeks 3-5

  • *Due: Reviewer Comments
WEEK 7
  • Start building the Correlator
  • Start implementing y-axis if possible

  • *Due: Final Design Package
WEEK 8
  • Finish building the Correlator
  • Build arm devices: camera, gun, laser, spotlight
  • Build the Aimer
  • *Due: Revised Final Design Package

 

WEEK 9
  • Building all component together
  • Flex Time/Debug

  • *Due: Reviewer Comments
WEEK 10
  • FLex Time/Debug

WEEK 11

 
  • Flex Time/Debug

  • *Due: Project Report
 

Previous     Next